11/14/07 Work on second floor inside.
11/7/07 Installing new window frames.
11/2/07 Facade finished, scaffolding taken down.
11/2/07 Facade almost completed.
10/29/07 More work on the EIFS.
10/24/07 Working on the EIFS. Scoring on the EIFS.
10/23/07 EIFS installed all around.
10/22/07 Instaling EIFS (Exterior Insulation Finis...
10/18/07 Topping off the brick facade and a peek i...
Working around the windows.
Insulation around the window areas.
Laying down the tarpaper.
►
October
(36)
About Me
Peter Stamoolis
View my complete profile
Monday, November 26, 2007
11/14/07 Work on second floor inside.
11/7/07 Installing new window frames.
11/2/07 Facade finished, scaffolding taken down.
Friday, November 23, 2007
11/2/07 Facade almost completed.
10/29/07 More work on the EIFS.
Wednesday, November 14, 2007
10/24/07 Working on the EIFS.
Scoring on the EIFS.
10/23/07 EIFS installed all around.
10/22/07 Instaling EIFS (Exterior Insulation Finish System, pronounced EEFIS), the white material above the brick.
10/18/07 Topping off the brick facade and a peek inside.
Moving the insullation to the 2nd floor.
Monday, November 5, 2007
Working around the windows.
Insulation around the window areas.
Laying down the tarpaper.